RECOMMENDATION OF MUNICIPALITIES IN AEP SERVICE TERRITORY

Electric utility restructuring; capped rates for municipalities.

§ 56-582. Rate caps.

A. The Commission shall establish capped rates, effective January 1, 2001, and expiring on July 1, 2007, for each service territory of every incumbent utility as follows:

1. Capped rates shall be established for customers purchasing bundled electric transmission, distribution and generation services from an incumbent electric utility.

2. Capped rates for electric generation services, only, shall also be established for the purpose of effecting customer choice for those retail customers authorized under this chapter to purchase generation services from a supplier other than the incumbent utility during this period.

3. The capped rates established under this section shall be the rates in effect for each incumbent utility as of the effective date of this chapter, or rates subsequently placed into effect pursuant to a rate application filed by an incumbent electric utility with the Commission prior to January 1, 2001, and subsequently approved by the Commission, and made by an incumbent electric utility that is not currently bound by a rate case settlement adopted by the Commission that extends in its application beyond January 1, 2002. If such rate application is filed, the rates proposed therein shall go into effect on January 1, 2001, but such rates shall be interim in nature and subject to refund until such time as the Commission has completed its investigation of such application. Any amount of the rates found excessive by the Commission shall be subject to refund with interest, as may be ordered by the Commission. The Commission shall act upon such applications prior to commencement of the period of transition to customer choice. Such rate application and the Commission's approval shall give due consideration, on a forward-looking basis, to the justness and reasonableness of rates to be effective for a period of time ending as late as July 1, 2007. The capped rates established under this section, which include rates, tariffs, electric service contracts, and rate programs (including experimental rates, regardless of whether they otherwise would expire), shall be such rates, tariffs, contracts, and programs of each incumbent electric utility, provided that experimental rates and rate programs may be closed to new customers upon application to the Commission.

B. The Commission may adjust such capped rates in connection with the following: (i) utilities' recovery of fuel costs pursuant to § 56-249.6, (ii) any changes in the taxation by the Commonwealth of incumbent electric utility revenues, (iii) any financial distress of the utility beyond its control, (iv) with respect to cooperatives that were not members of a power supply cooperative on January 1, 1999, and as long as they do not become members, their cost of purchased wholesale power and discounts from capped rates to match the cost of providing distribution services, and (v) with respect to cooperatives that were members of a power supply cooperative on January 1, 1999, their recovery of fuel costs, through the wholesale power cost adjustment clauses of their tariffs pursuant to § 56-226. Notwithstanding the provisions of § 56-249.6, the Commission may authorize tariffs that include incentives designed to encourage an incumbent electric utility to reduce its fuel costs by permitting retention of a portion of cost savings resulting from fuel cost reductions or by other methods determined by the Commission to be fair and reasonable to the utility and its customers.

C. A utility may petition the Commission to terminate the capped rates to all customers any time after January 1, 2004, and such capped rates may be terminated upon the Commission finding of an effectively competitive market for generation services within the service territory of that utility. If the capped rates are continued after January 1, 2004, an incumbent electric utility which is not, as of the effective date of this chapter, bound by a rate case settlement adopted by the Commission that extends in its application beyond January 1, 2002, may petition the Commission for approval of a one-time change in the nongeneration components of such rates.

D. Until the expiration or termination of capped rates as provided in this section, the incumbent electric utility, consistent with the functional separation plan implemented under § 56-590, shall make electric service available at capped rates established under this section to any customer in the incumbent electric utility's service territory, including any customer that, until the expiration or termination of capped rates, requests such service after a period of utilizing service from another supplier.

E. During the period when capped rates are in effect for an incumbent electric utility, such utility may file with the Commission a plan describing the method used by such utility to assure full funding of its nuclear decommissioning obligation and specifying the amount of the revenues collected under either the capped rates, as provided in this section, or the wires charges, as provided in § 56-583, that are dedicated to funding such nuclear decommissioning obligation under the plan. The Commission shall approve the plan upon a finding that the plan is not contrary to the public interest.

F. Capped rates for municipalities and other governmental customers purchasing bundled electric transmission, distribution and generation services for governmental uses from an incumbent utility, unless otherwise mutually agreed by the municipality and the utility, shall be the rates in effect or billed for each incumbent utility as of January 1, 2001 and to continue until July 1, 2007; however, if the Commission makes any adjustments to, or termination of, capped rates pursuant to subsection B or C of this section, the municipalities or other governmental customers and incumbent utility shall make any similar adjustment or termination of capped rates unless otherwise mutually agreed.

§ 56-583. Wires Charges.

A. To provide the opportunity for competition and consistent with § 56-584, the Commission shall calculate wires charges for each incumbent electric utility, effective upon the commencement of customer choice, which shall be the excess, if any, of the incumbent electric utility's capped unbundled rates for generation over the projected market prices for generation, as determined by the Commission; however, where there is such excess, the sum of such wires charges, the unbundled charge for transmission and ancillary services, the applicable distribution rates established by the Commission and the above projected market prices for generation shall not exceed the capped rates established under § 56-582 A 1 applicable to such incumbent electric utility. The Commission shall adjust such wires charges not more frequently than annually and shall seek to coordinate adjustments of wires charges with any adjustments of capped rates pursuant to § 56-582. No wires charge shall be less than zero. The projected market prices for generation, when determined under this subsection, shall be adjusted for any projected cost of transmission, transmission line losses, and ancillary services subject to the jurisdiction of the Federal Energy Regulatory Commission which the incumbent electric utility (i) must incur to sell its generation and (ii) cannot otherwise recover in rates subject to state or federal jurisdiction.

B. Customers that choose suppliers of electric energy, other than the incumbent electric utility, or are subject to and receiving default service, prior to the expiration of the period for capped rates, as provided for in § 56-582, shall pay a wires charge determined pursuant to subsection A based upon actual usage of electricity distributed by the incumbent electric utility to the customer (i) during the period from the time the customer chooses a supplier of electric energy other than the incumbent electric utility or (ii) during the period from the time the customer is subject to and receives default service until capped rates expire or are terminated, as provided in § 56-582.

C. The Commission shall permit any customer, at its option, to pay the wires charges owed to an incumbent electric utility on an accelerated or deferred basis upon a finding that such method is not (i) prejudicial to the incumbent electric utility or its ratepayers or (ii) inconsistent with the development of effective competition, provided that all deferred wires charges shall be paid in full by July 1, 2007.

D. A supplier of retail electric energy may pay any or all of the wires charge owed by any customer to an incumbent electric utility. The supplier may not only pay such wires charge on behalf of any customer, but also contract with any customer to finance such payments. Further, on request of a supplier, the incumbent electric utility shall enter into a contract allowing such supplier to pay such wires charge on an accelerated or deferred basis. Such contract shall contain terms and conditions, specified in rules and regulations promulgated by the Commission to implement the provisions of this subsection, that fully compensate the incumbent electric utility for such wires charge, including reasonable compensation for the time value of money.

E. The determination of market prices for generation and the calculation of, and subsequent adjustments to, wires charges applicable to municipalities and other governmental customers shall be consistent with and based on the same methodologies as approved by the Commission unless otherwise mutually agreed.

Privacy Statement | Legislative Services | General Assembly