Capacity Obligations are established under the provisions of the Reliability Assurance Agreement.
- The Installed Reserve Requirement (IRM) for each planning period (June 1 - May 31) is set two years prior to the start of the planning period.
- The IRM establishes the capacity required, above peak load, to ensure the reliability of the control area.
- Zonal obligations are set based on the the zones contribution to the PJM coincident peak .
- Obligations are calculated daily for each Load Serving Entity (LSE) based on customer allocation and customer peak load contribution.
-
-